States / Federal (Davis-Bacon) / What are the penalties for late, missing or false certified payroll?

What are the penalties for late, missing or false certified payroll?

On federal and federally assisted construction jobs, late, missing or false certified payroll can lead to withheld contract payments, suspension of payments until the records come in, back wages with interest, debarment for 3 years under 29 CFR 5.12, and civil or criminal prosecution for falsification under 18 U.S.C. 1001 and 31 U.S.C. 3729. Since the 2023 rule, money can also be withheld from other contracts held by the same prime.

What happens if a certified payroll is late or missing?

The agency can stop paying the contract. Certified payroll is due weekly, within 7 days after the regular payment date for the payroll period (29 CFR 3.4(a)). If a contractor or subcontractor fails to submit the required records, the agency may, after written notice, take action to suspend any further payment, advance or guarantee of funds until the violation stops (29 CFR 5.5(a)(2)(i) and (a)(3)(iv)(B)).

The same paragraph adds two more consequences:

  • Failing to submit records on request, make them available, or allow worker interviews on the job can be grounds for debarment under 29 CFR 5.12.
  • A contractor that doesn't produce required records to the DOL's Wage and Hour Division within the time it asks can't use those records later as evidence in an administrative proceeding under 29 CFR part 6. WHD considers reasonable requests for more time.

Because the prime is responsible for submitting every subcontractor's certified payroll (29 CFR 5.5(a)(3)(ii)(A)), a sub's missing payroll is the prime's responsibility too.

What happens if workers were underpaid?

The contractor owes back wages, with interest. When an underpayment is found, the agency or DOL asks for restitution to the workers, or to their fringe benefit plans, with interest from the date of the underpayment. Interest is figured at the IRS underpayment rate under 26 U.S.C. 6621 and compounded daily (29 CFR 5.10(a)).

To cover it, the agency may withhold accrued payments on its own, and must withhold when DOL asks in writing (29 CFR 5.5(a)(2)(i)). DOL can pay the workers directly from the withheld money. If that isn't enough, workers can sue the contractor and its sureties (40 U.S.C. 3144(a)). DOL's claim to withheld funds comes ahead of sureties, the agency's reprocurement costs, bankruptcy trustees, assignees, successors and Prompt Payment Act claims (29 CFR 5.5(a)(2)(ii)).

On contracts over $100,000 that are subject to the Contract Work Hours and Safety Standards Act, unpaid overtime also carries liquidated damages of $33 per worker for each calendar day the worker worked over 40 hours in the week without the overtime pay (29 CFR 5.5(b)(2)).

Can a contractor be debarred?

Yes, for 3 years. When the Secretary of Labor finds that a contractor or subcontractor disregarded its obligations to workers or subcontractors, the contractor, its responsible officers and any firm they have an interest in become ineligible for 3 years for any federal contract or subcontract and any contract covered by the Davis-Bacon and Related Acts (29 CFR 5.12(a)). Names are published on SAM.gov, and the 3 years run from the date of publication. The statute bars awards to listed contractors for the same 3 years (40 U.S.C. 3144(b)).

Before debarment, DOL sends notice of its findings, and the contractor has 30 days to request a hearing (29 CFR 5.12(b)). A breach of the contract clauses can also be grounds for terminating the contract (29 CFR 5.5(a)(7)). By signing a covered contract, a contractor certifies it isn't debarred, and a covered contract can't be subcontracted to a debarred firm (29 CFR 5.5(a)(10)).

What changed in the 2023 rule for primes and cross-withholding?

Two things reach past the sub that made the mistake. The DOL's final rule was published August 23, 2023 (88 FR 57526), took effect October 23, 2023, and applies to contracts entered into after that date.

Cross-withholding. Money to cover back wages can be withheld from the contract where the violation happened, from any other federal contract with the same prime, or from any other federally assisted contract with the same prime that's subject to Davis-Bacon labor standards, even if a different agency awarded it (29 CFR 5.5(a)(2)(i) and 5.9(b)). The rule's definition of "prime contractor" includes controlling shareholders or members, joint venture partners, and a general contractor delegated to oversee all or substantially all of the construction, and related entities count as the same prime (29 CFR 5.2). Cross-withholding from a different legal entity's contract requires that its contract included the withholding clause (29 CFR 5.9(c)).

Flow-down liability. The subcontract clause in the 2023 rule says the prime is responsible for compliance by every subcontractor and lower-tier sub. If the clauses are violated, the prime and any responsible subcontractors are liable for unpaid wages and monetary relief, with interest, owed to workers of lower-tier subs, and may be debarred (29 CFR 5.5(a)(6)).

On June 24, 2024, a federal court in the Northern District of Texas enjoined three other provisions of the rule, none of them the withholding, flow-down or debarment provisions above. DOL's page says the rest of the rule remains in effect.

What are the penalties for a false certified payroll?

Criminal and civil. The regulation says falsifying the statement of compliance may subject the contractor or subcontractor to civil or criminal prosecution under 18 U.S.C. 1001 and 31 U.S.C. 3729 (29 CFR 5.5(a)(3)(ii)(F)), and the Copeland Act applies section 1001 to the weekly wage statements (40 U.S.C. 3145(b)).

Law What it covers Penalty in the statute
18 U.S.C. 1001 Knowingly and willfully making a materially false statement or document A fine, up to 5 years in prison, or both
31 U.S.C. 3729 (False Claims Act) Knowingly making a false record or statement material to a false claim for payment A civil penalty of $5,000 to $10,000 per violation as adjusted for inflation, plus 3 times the government's damages and the costs of the suit
29 CFR 5.12 Disregard of obligations to workers or subcontractors Debarment for 3 years

The warning above the signature line on the WH-347 (Rev. January 2025) says willful falsification may bring civil or criminal prosecution under those two statutes and debarment. When an agency or DOL finds substantial evidence that violations are willful and break a criminal statute, the matter goes to the Attorney General (29 CFR 5.10(b)).

What about state prevailing wage jobs?

This page covers the federal rules. For a job under a state prevailing wage law, see the state's page: California, New York, New Jersey, Illinois, Washington, Massachusetts, Pennsylvania, Ohio, Maryland and Oregon.

Sources

  1. eCFR, Office of the Federal Register, 29 CFR 5.5, Contract provisions and related matters. Interest on underpayments (a)(1)(vi); withholding, cross-withholding and suspension for failure to pay or submit records (a)(2)(i); DOL priority to withheld funds (a)(2)(ii); weekly submission and the prime's responsibility for subs' payrolls (a)(3)(ii)(A); falsification under 18 U.S.C. 1001 and 31 U.S.C. 3729 (a)(3)(ii)(F); suspension, debarment and exclusion of records not produced (a)(3)(iv)(B); prime and sub liability for lower-tier workers (a)(6); termination and debarment (a)(7); certification of eligibility (a)(10); CWHSSA overtime liquidated damages of $33 a day (b)(2).. Checked October 19, 2026.
  2. eCFR, Office of the Federal Register, 29 CFR 5.9, Suspension of funds. Suspension of payment until violations stop or enough is withheld; cross-withholding from other contracts of the same prime; cross-withholding from related legal entities.. Checked October 19, 2026.
  3. eCFR, Office of the Federal Register, 29 CFR 5.10, Restitution, criminal action. Restitution of back wages and fringes with interest at the 26 U.S.C. 6621 underpayment rate, compounded daily; willful violations referred to the Attorney General.. Checked October 19, 2026.
  4. eCFR, Office of the Federal Register, 29 CFR 5.12, Debarment proceedings. Disregard of obligations leads to 3-year ineligibility for the contractor, responsible officers and firms with an interest; names published on SAM; 3 years from publication; notice and 30 days to request a hearing.. Checked October 19, 2026.
  5. eCFR, Office of the Federal Register, 29 CFR 5.2, Definitions (Prime contractor). Prime contractor includes controlling shareholders or members, joint venturers or partners, and a contractor delegated to oversee all or substantially all of the construction; related entities treated as the same prime for 5.5 and 5.9.. Checked October 19, 2026.
  6. eCFR, Office of the Federal Register, 29 CFR 3.4, Submission of certified payroll and the preservation and inspection of weekly payroll records. Certified payroll is due within 7 days after the regular payment date of the payroll period.. Checked October 19, 2026.
  7. Federal Register, via U.S. Government Publishing Office (govinfo), Updating the Davis-Bacon and Related Acts Regulations, Final Rule (88 FR 57526, August 23, 2023). Effective October 23, 2023 and applicable to contracts entered into after that date; the rule's text of 5.5(a)(6) on prime and subcontractor liability for lower-tier workers; the new prime contractor definition puts primes on notice of liability for subcontractor violations.. Checked October 19, 2026.
  8. U.S. Department of Labor, Wage and Hour Division, Final Rule: Updating the Davis-Bacon and Related Acts Regulations. The June 24, 2024 Northern District of Texas preliminary injunction against three provisions (material suppliers, delivery truck drivers, and operation of law at 5.5(e)); the rest of the rule remains in effect.. Checked October 19, 2026.
  9. U.S. Government Publishing Office (govinfo), 40 U.S.C. 3144, Authority to pay wages and list contractors violating contracts. DOL pays workers directly from withheld funds; workers can sue the contractor and its sureties; no contract to listed persons or firms they have an interest in until 3 years after the list is published.. Checked October 19, 2026.
  10. U.S. Government Publishing Office (govinfo), 40 U.S.C. 3145, Regulations governing contractors and subcontractors. Each contractor and subcontractor furnishes a weekly statement of wages paid; 18 U.S.C. 1001 applies to those statements.. Checked October 19, 2026.
  11. U.S. Government Publishing Office (govinfo), 18 U.S.C. 1001, Statements or entries generally. Knowingly and willfully making a materially false statement or document: a fine, up to 5 years in prison, or both.. Checked October 19, 2026.
  12. U.S. Government Publishing Office (govinfo), 31 U.S.C. 3729, False claims. Civil penalty of $5,000 to $10,000 per violation as adjusted for inflation, plus 3 times the government's damages, plus the costs of the civil action.. Checked October 19, 2026.
  13. U.S. Department of Labor, Wage and Hour Division, Davis-Bacon and Related Acts Weekly Certified Payroll Form (WH-347), Rev. January 2025. The warning above the signature: willful falsification may bring civil or criminal prosecution under 18 U.S.C. 1001 and 31 U.S.C. 3729 and debarment.. Checked October 19, 2026.

Join the Davis-Bacon waitlist

We’ll email you when certified payroll opens for your jobs. One email, no calls.

We’re building Davis-Bacon certified payroll: your payroll imported, rates compared with the wage determination you pick, and the report ready for your signature.

More about Davis-Bacon certified payroll

What does the WH-347 statement of compliance certify?

Page 2 of the WH-347 is the statement of compliance. On the January 2025 form it has six check boxes: payroll correct and rates paid, records kept, classifications correct, apprentices registered, fringe benefits paid, and no rebates or improper deductions. Boxes 1, 2, 3 and 6 are always checked. The contractor, or the agent who pays or supervises pay, signs it, and the DOL says a false statement is subject to 18 U.S.C. 1001.

How do you read a Davis-Bacon wage determination?

A Davis-Bacon wage determination is the DOL's list of minimum hourly rates and fringes for each classification on a covered construction job. Your contract names the WD number and modification number, and the WD is posted on SAM.gov. Each line gives a rate identifier, the classification, the base rate and the fringe. The modification that applies is generally the one in effect at bid opening or award, under 29 CFR 1.6.

What are the apprentice rules on a Davis-Bacon job?

On a Davis-Bacon job, a worker can be paid below the wage determination rate only as an apprentice individually registered in a program registered with the DOL's Office of Apprenticeship or a recognized State Apprenticeship Agency. Pay is the program's percentage of the journeyworker rate, the ratio is the one for the job's locality, and unregistered or over-ratio workers get the full rate for the work they perform, under 29 CFR 5.5(a)(4).

What is certified payroll?

Certified payroll is the weekly payroll report a contractor or subcontractor on a prevailing wage public works job submits, with a signed statement of compliance saying every worker was paid at least the required rate. On federal and federally assisted construction contracts over $2,000, the Davis-Bacon and Related Acts require it every week, on the DOL's optional WH-347 or any format with the same information. States with prevailing wage laws set their own rules.

How to fill out the WH-347, line by line

The WH-347 is the Department of Labor's optional weekly certified payroll form for Davis-Bacon jobs. The current version is dated January 2025 (OMB No. 1235-0008, expires January 31, 2028). Page 1 lists each worker's classification, daily hours, rates, fringe credit, gross pay, deductions and net pay in columns 1A to 9. Page 2 is the signed statement of compliance. Both go in every week, and the prime is responsible for submitting its subcontractors' payrolls.